Vår Energi – Jotun FPSO – management of barriersPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Vår Energi’s management of barriers on Jotun FPSO within the domain of process integrity.
- Process safety
- Barrier management
- Maintenance management
-
Equinor – Johan Sverdrup phase 2 – overpressure protection of inlet arrangements and leak detection for subsea facilitiesPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and the overpressure protection of inlet arrangements on the Johan Sverdrup phase 2 processing platform P2, and leak detection for associated subsea templates.
-
AoC audit – Noble Drilling – Noble Lloyd Noble – emergency preparedness, helideck and drinking waterPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Noble Drilling Norway AS (Noble Drilling) in connection with the company’s application for an Acknowledgement of Compliance (AoC) for Noble Lloyd Noble.
- Emergency preparedness
-
Equinor – materials selection and fabricationPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and the parts of the organisation that are responsible for materials selection and fabrication.
-
Equinor Transportnett – transport pipelinesPublished:The Petroleum Safety Authority Norway has carried out an audit of Equinor Transportnett concerning the integrity of transport pipelines.
-
Equinor – Johan Castberg – cranes, lifting equipment and materials handlingPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor within cranes, lifting equipment and materials handling for Johan Castberg.
- Handling, cranes and lifting
- Emergency preparedness
- Structural safety
- Risk management
-
Transocean – Transocean Barents – management of stability, watertight and weathertight integrity and the ballast systemPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Transocean Services AS (Transocean) and the management of stability, watertight and weathertight integrity, the ballast system, waves in deck and positioning for Transocean Barents.
-
Repsol – follow-up of management practicePublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Repsol and its follow-up of its own management practice.
-
Equinor – follow-up of management practicePublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and its follow-up of its own management practice.
-
Equinor – Halten Øst project – development conceptPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of Equinor and the Halten Øst project, and the decision concerning the development concept.
- Risk management
- Structural safety
- Process safety