Statoil - Heimdal - Monitoring of major-accident and OHAS riskPublished:From 24 March to 18 June 2014, the PSA carried out an audit of Statoil Petroleum AS (Statoil)'s monitoring of major-accident and OHAS risk associated with a modular drilling rig (MDR) in temporary use for well plugging at the Heimdal facility.
- Working environment
- Risk management
-
GDF SUEZ - Gjøa - Barrier management, process safety, technical safety and electrical installationsPublished:From 5 to 8 May 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of GDF SUEZ E&P Norge AS (GDF) on board the Gjøa facility.
- Barrier management
- Process safety
- Technical safety
- Electrical installations
-
Statoil - Tjeldbergodden - Electrical installationsPublished:From 11 to 13 June 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of electrical installations at Tjeldbergodden.
- Electrical installations
-
Rowan Norway - Rowan Gorilla VI - Maintenance management, logistics (cranes and lifting), drilling and well technology, and emergency preparednessPublished:On 17 and 18 June 2014, the Petroleum Safety Authority Norway carried out an audit of Rowan Norway Limited and Rowan Gorilla VI within the disciplines of maintenance management, logistics (cranes and lifting), drilling and well technology, and emergency p
- Maintenance management
- Handling, cranes and lifting
- Well integrity
- Emergency preparedness
-
Statoil - Statfjord C - Barrier managementPublished:From 23 to 25 April 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil's barrier management at Statfjord C.
- Barrier management
-
Premier Oil - Bream - Project management, risk management and technical barriersPublished:On 29 April 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Premier Oil's management of the early phase of the Bream project prior to the plan for development and operation (PDO).
- Risk management
- Technical safety
- Barrier management
-
Statoil - Johan Sverdrup - Management of development projectPublished:On 13 March 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil's management of the early phase of the Johan Sverdrup project prior to the plan for development and operation (PDO).
- Risk management
-
Statoil - Johan Sverdrup - Barrier managementPublished:On 20 and 21 May 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil's barrier management in the early phase of the Johan Sverdrup project prior to the plan for development and operation (PDO).
- Barrier management
-
ExxonMobil - Jotun A - emergency preparednessPublished:We have carried out an audit of ExxonMobil Exploration and Production Norway AS (ExxonMobil)’s management of emergency preparedness at Jotun A and in 2nd-line emergency response on land.
- Emergency preparedness
-
Order to Prosafe AS following audit of at-risk groups on RegaliaPublished:From 25 to 28 May 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of Prosafe AS’s systems and practices for the identification and follow-up of potentially at-risk groups. The audit also concerned arrangements for employee participa