The objective of the audit was to monitor how Eni ensures compliance with the barrier requirements in a comprehensive and consistent manner, in order to reduce risk to the greatest extent possible.

Result

One non-conformity was identified in connection with fire water supply.

No improvement points were identified.

Eni has been given a deadline of 30 August 2015 to report on how the non-conformity will be dealt with.

Non-conformity:

Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:

Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.