Audit reports
We publish all of our audit reports to facilitate learning and transfer of experience.
Read more about our supervision
Sorted by:
Most recently published
-
Statoil - Grane - Lifting equipment and maintenance managementPublished:From 11 to 13 May 2015, the Petroleum Safety Authority Norway (PSA) carried out an audit of Statoil's control and management of materials handling, the technical condition of lifting equipment and the company's management of lifting equipment maintenance.
- Well integrity
- Handling, cranes and lifting
- Maintenance management
-
ConocoPhillips - Ekofisk 2/4-L - Environmental data collectionPublished:From 5 to 7 May 2015, the PSA, in collaboration with the Norwegian Meteorological Institute, carried out an audit of ConocoPhillips' management of environmental data collection at the Ekofisk Centre.
- Technical safety
- Maintenance management
-
Statoil og Maersk Drilling Norge AS - Maersk Gallant - Drilling operationsPublished:Between 16 and 20 March 2015, the PSA carried out an audit of Statoil and Maersk Drilling concerning HPHT drilling operations at the 2/4-22 Romeo and 2/4-23 Julius exploration wells using Maersk Gallant.
- Working environment
- Well integrity
- Barrier management
-
Shell - Nyhamna - Barrier management and risk managementPublished:On 11 May 2015, the Petroleum Safety Authority Norway (PSA) carried out an audit of Shell and the development project at Nyhamna within the disciplines of barrier management and risk management.
- Barrier management
- Risk management
-
Statoil - Åsgard A - BarriersPublished:From 23 to 26 March 2015, the Petroleum Safety Authority Norway (PSA) performed an audit of the Åsgard A facility.
- Barrier management
- Risk management
-
Order for Statoil - Oseberg B and Gullfaks C - Drilling and wellPublished:The PSA has issued an order to Statoil following audits at Oseberg B and Gullfaks C.
- Well integrity
-
Shell - Non-conformity handlingPublished:On 6 March 2015, the Petroleum Safety Authority Norway carried out an audit of Norske Shell's non-conformity handling.
- Emergency preparedness
- Well integrity
- Structural safety
-
Statoil Aasta Hansteen - Development projectPublished:From 14 to 16 April 2015, the Petroleum Safety Authority Norway carried out an audit of Statoil and the development of Aasta Hansteen.
-
Det norske – the company’s follow-upPublished:We have carried out an audit of Det norske oljeselskap ASA (Det norske) and their own follow-up.
- Working environment
- Risk management
- Structural safety
- Well integrity
-
Gassco - Removal of the B11 facilityPublished:Between 14 and 27 March 2015, the Petroleum Safety Authority Norway carried out an audit of Gassco and the removal of the B11 facility.
- Handling, cranes and lifting
- Working environment
- Risk management