The audit was conducted on 8 and 9 June 2026.
Objective
The objective was to conduct an audit of Harbour Energy and the Dvalin Nord project, with a focus on the project's completion and transition to operational status. We paid particular attention to:
- Project management and project control
- Experiences and lessons learned, particularly from the launch of Dvalin in 2023
- Non-conformity handling and changes since the PDO
- The transition from project to operation, with a particular focus on the change from Wintershall Dea to Harbour Energy, as well as a subsequent, recently completed, internal reorganisation
- Completion and testing
- Barrier management
Result
We identified one non-conformity related to deficiencies in the handling of non-conformities. In addition, an improvement point was identified concerning necessary resources.
What happens now?
We have asked Harbour Energy to report to us by 28 August 2026 on how the non-conformity will be addressed, and to give us their assessment of the improvement point observed.