The audit was undertaken in combination with Okea’s Draugen power-from-shore project, since the two projects are closely linked.

Objective

The objective of the audit was to ensure that the electrification project is being carried out in compliance with applicable regulations, with a particular focus on the Management Regulations and the Activity Regulations.

Result

No non-conformities were detected during this audit.

Two improvement points were identified concerning:

  • Roles, responsibilities and employee participation
  • Plans for different operational scenarios

What happens next?

We have asked Equinor to give us their assessment of the improvement points observed by 1 August 2026.