The audit was conducted from 21 to 23 April 2026.

Objective

The objective of the audit was to verify that OKEA has designed and documented regulatory compliance of the solutions chosen for overpressure protection of the inlet system for Bestla’s tie-back to Brage.

Result

The audit identified no non-conformities, but we observed three matters that we have chosen to categorise as improvement points. This concerned:

  • Inadequate overpressure protection of the inlet system 
  • Inadequate documentation 
  • Inadequate analysis 

What happens now?

We have asked OKEA to report to us by 21 august 2026 for their assessment of the improvement points observed.