The audit was conducted on 23 April 2026.

Objective

The objective of the audit was to obtain an overview of the technical condition and integrity of the pipeline systems for which Transportnett has operational responsibility, and to verify that their operation complies with the requirements in the HSE regulations.

Result

We did not identify any non-conformities or improvement points in this audit.