The audit was conducted on 20 and 21 March 2024.

Objective

The objective of the audit was to verify that the company has established systems for condition monitoring, maintenance and repairs of structures that form part of the jetties at the Sture terminal, so that the likelihood of faults, hazards and accident situations is reduced. Furthermore, we wanted to promote increased focus on the necessary condition monitoring and maintenance of the jetties as an important part of the plant’s infrastructure.

Result

We did not identify any non-conformities during the audit, but observed three areas with potential for improvement. These concerned:

  • Follow-up of identified maintenance needs
  • Follow-up of maintenance management
  • Documentation of analyses

What happens now?

We have asked Equinor to give us their assessment of the improvement points observed by 24 May 2024.