The audit was carried out between 18 and 21 November 2019.

When the audit was conducted Floatel Endurance was in use as a floatel on the Martin Linge field, where Equinor is the operator.

The audit covered the bridge systems on Floatel Endurance for positioning and the technical systems for the gangway between Floatel Endurance and the Martin Linge A facility.

Result

No non-conformities were identified during the audit, but we observed two improvement points. These concerned criteria for interrupting activities and the presentation of information.

What happens now?

We have asked Floatel International for their assessment of the improvement points we observed. The deadline for feedback is set at 3 February 2020.