Due to the extra work on the Goliat field, Eni requires more cabin capacity, and has therefore applied to the PSA for consent to use the Floatel Endurance mobile accommodation facility as a floatel.

We have granted Eni consent for this.

Floatel Endurance will be dynamically positioned and linked to the Goliat facility by a telescopic footbridge.

The consent applies for the period 20 August to 15 November 2017.

Floatel Endurance is a semi-submersible accommodation facility delivered by the Keppel FELS yard in Singapore in 2015. It is owned and will be operated by Floatel International AB of Sweden. The facility was issued with an Acknowledgement of Compliance (AoC) by the PSA in 2016.