Audit reports
We publish all of our audit reports to facilitate learning and transfer of experience.
Read more about our supervision
Sorted by:
Most recently published
-
Equinor – Johan Castberg – preservation of equipment and systemsPublished:From 14 to 28 September 2020, we carried out an audit of the preservation of equipment and systems for Johan Castberg at the construction sites at Stord and Egersund.
- Well integrity
- Process safety
- Risk management
-
Order to Equinor – Hammerfest LNG – major accident and electrical installationsPublished:The PSA has audited Equinor ASA with regard to major accidents and electrical installations at Hammerfest LNG. Serious breaches of the regulations related to handling of nonconformities were identified, and the company has now been issued with an order.
- Process safety
- Electrical installations
-
Seadrill – West Phoenix – stability, watertight and weathertight integrity and ballast systemsPublished:We have carried out an audit of Seadrill and their management of stability, watertight and weathertight integrity and ballast systems for the West Phoenix mobile drilling facility.
- Structural safety
-
Rowan (Valaris) – Rowan Stavanger – data security for industrial ICT systemsPublished:We have carried out an audit of Rowan Norway (Valaris) and their management of risks linked to data security of the industrial ICT systems for the Rowan Stavanger mobile drilling facility.
- Cyber security
-
Equinor – Operations South and FLX - infield pipelines, risers and control cablesPublished:We have carried out an audit of Equinor Energy (Equinor) focused on operational follow-up and integrity management of infield pipelines, risers and control cables from the Operations South and Field Life Extension (FLX) areas.
- Structural safety
-
Aker BP – Hod – design engineering of steel jacket and foundationsPublished:We have carried out an audit of Aker BP and their management of the design engineering of the steel jacket and foundations for the Hod field.
- Structural safety
-
ConocoPhillips/Transocean – planning and execution of drilling and well activitiesPublished:The Petroleum Safety Authority Norway (PSA) has carried out an audit of ConocoPhillips, Transocean and associated drilling service contractors’ undertaking of the planning and execution of exploration well 6507/4-1.
- Well integrity
-
Neptune Energy – Gjøa – follow-up of ongoing projectsPublished:We have carried out an audit of Neptune Energy and their follow-up of development projects due to be tied to the Gjøa field.
- Technical safety
- Process safety
- Electrical installations
-
Norske Shell – Ormen Lange/Nyhamna – operation and maintenance of pipelines, subsea facilities and onshore installationsPublished:We have carried out an audit of Norske Shell focused on the operation and maintenance of pipelines, subsea facilities and onshore installations for Ormen Lange and Nyhamna.
- Structural safety
-
Vår Energi – Goliat – structural integrity and maritime systemsPublished:We have carried out an audit of Vår Energi focused on the company’s safeguarding of the integrity of structures and maritime systems on the Goliat field.
- Structural safety