The audit was conducted from 3 to 6 June 2025.
Objective
The objective of the audit was to monitor how the company complies with the regulatory requirements for electrical facilities, and work in and operation of electrical facilities.
Result
One non-conformity was identified concerning overcurrent protection.
In addition, two improvement points were identified, concerning:
- Conduct of internal inspections of electrical facilities
- Overview and control of temporary equipment
What happens next?
We have asked Equinor to report by 1 September 2025 on how the non-conformities will be addressed and for their assessment of the improvement points observed.