The audit was conducted on 22 May 2025.

Objective
The objective of the audit was to monitor that the project is being carried out in compliance with the HSE regulations and that, in its project management and follow-up, Equinor is reducing risk and preventing accidents during start-up and operation.

Result

No non-conformities were identified.

Four improvement points were identified, concerning:

  • Decision support and decision-making criteria for HSE related to the Project Change Proposal
  • Measurement parameters and indicators
  • Analysis of the working environment in the control room
  • Non-conformity registration

What happens next?

We have asked Equinor to give us its assessment of the improvement points observed by 15 September 2025.