The audit was conducted from 21 to 31 October 2024.

Objective

The objective of the audit was to verify systems and processes that contribute to ensuring

  • comprehensive management of emergency preparedness, in accordance with regulatory requirements.
  • that Aker BP undertakes systematic work to reduce the risks associated with helicopter operations.
  • safe materials handling and safe lifting operations, including follow-up and post-incident learning.

Result

The audit identified eight non-conformities. These concerned:

  • Defective maintenance of perimeter lights on the helideck
  • Deficient anti-slip protection on the helideck
  • Deficient marking of obstacles
  • Boat hook does not have metal shaft
  • Efficient and safe materials handling
  • Bunkering hose stations
  • Inadequate follow-up of loose lifting equipment
  • Deficiencies in lifeboat maintenance system

We also observed six factors that we have chosen to categorise as improvement points. These concerned:

  • Helideck lighting
  • Paints of contrasting colours on helideck
  • Offshore crane
  • Roles and responsibilities in the safe use of lifting equipment
  • Deficiencies in the system to ensure competence of emergency response teams
  • Lack of human-machine interface for workstation for maritime surveillance

What happens now?

We have asked Aker BP to report to us by 31 January 2025 on how the non-conformities will be addressed, and to give us their assessment of the improvement points observed.