The audit was conducted on 10 and 11 May 2023. 

Objective

The objective of the audit was to monitor Vår Energi’s operation and maintenance of pipelines, risers and subsea facilities, and to ensure they have a holistic approach to safe operation in accordance with regulatory requirements.

Result

The audit identified no non-conformities.

One improvement point was identified concerning the updating of documentation.

What happens next?

We have asked Vår Energi for their assessment of the improvement point identified. The reply deadline is set at 15 August 2023.