The audit was conducted from 3 to 5 June 2020.
Background
Equinor has decided to organise the operation of facilities in late life into a separate unit – FLX (field life extension). The unit became operational on 1 April 2020. Operation of the Statfjord field comes under the remit of this new unit.
The audit forms part of our long-term follow-up of Equinor’s maintenance management.
Objective
The objective of the audit was to monitor that Equinor’s maintenance of management in the FLX unit complies with the regulations and the company’s own requirements. Furthermore, the objective was to ensure that key contributors to HSE risk and associated uncertainty are identified and followed up.
Result
We did not identify any non-conformities or improvement points in this audit.