Objective

The objective of the audit was to review relevant routines for performing, maintaining and reporting the collection of environmental data at Gullfaks C and to assess the technical standard of systems and equipment.

Result

No non-conformities were identified.

Two improvement points were identified in connection with:

  • Training
  • Measurement of sea temperatures

Statoil Petroleum AS has been given a deadline of 23 March 2018 to report on how the improvement points will be addressed.