The audit was conducted on 26 September 2018.

Objective

The objective of the audit was to verify the effect of measures taken following our audit of November 2016 focused on alarm load and human factors in the central control room of the Nyhamna installation. The results of this audit are available here.

Result

We identified no non-conformities or improvement points during this audit.