Objective

The audit took place at Teekay's premises in Stavanger on 9 and 10 May 2017. Teekay has signed a contract with Statoil on the use of the former shuttle tanker Randgrid, which is being converted in Singapore to use as the Gina Krog FSO.

The object of the audit was to gain an impression of whether the load-bearing structures and maritime systems will satisfy the regulatory requirements, and to ensure that the final documentation of the design and fabrication demonstrate compliance with regulations and relevant standards.

Result

No non-conformities were detected or improvement points identified during the audit.

Due to the delays in the project, many maritime systems were still in completion testing and associated documents and certificates were not available. We therefore did not examine all the documentation it was planned to review. We have asked Statoil to arrange a meeting when the testing has been completed.

Gina Krog

Gina Krog is a field on the Utsira High in the central part of the North Sea, just north of the Sleipner Vest field. The water depth in the area is 110-120 metres. Gina Krog was discovered in 1978, and the plan for development and operation (PDO) was approved in 2013. The field is developed with a fixed platform with living quarters and processing facilities. Drilling is performed by a mobile jack-up rig. Production started in 2017.