Objective
The objective of the audit was to verify the companies' safeguarding of governing documents, operational management and technical solutions ensuing from the use of pressure-balanced drilling equipment and new solutions for well control and blowout prevention.
Result
No non-conformities were identified.
Improvement points were identified in connection with:
- Competence
- The maintenance system
- Technical conditions
Total has been given a deadline of 1 August 2016 to report on how the improvement points will be dealt with.