Objective
The objective of the audit was to verify that integrity and barrier management for flexible risers and jumpers and associated equipment such as ESD and pressure relief equipment complied with the company's own requirements and statutory regulations.
Result
No non-conformities were identified.
Improvement points were identified in connection with the governing documents and materials requirements.
Statoil has been given a deadline of 31 August 2016 to report on how the improvement points will be dealt with.