Mål
We wanted to perform spot checks at an early stage of whether the set-up for verification complied with the Facilities Regulations, Section 56 concerning load-bearing structures and NORSOK N-001 item 5.2.
Resultat
No non-conformities were detected during this audit.
An improvement point was identified concerning the control of analyses.
Statoil has been given a deadline of 11 June 2016 to report on how the improvement point will be dealt with.