Objective
The objective of the audit was to monitor that Statoil, in cooperation with DSME/Aker Solutions and other stakeholders, was complying with the preconditions in the PDO, applicable regulations, standards and Statoil's own requirements. The audit placed particular emphasis on the implementation and visibility of Gina Krog's specific barrier strategies, performance requirements and performance-influencing factors from a life-cycle perspective.
Result
No non-conformities were identified.
Three improvement points were identified relating to:
- The barrier management system
- The emergency shutdown system
- Fire pumps