Objective
The objective of the audit of DPN Operations North/Åsgard/Åsgard B was to verify that the company's changes have been implemented and followed up in compliance with the authorities' requirements, including the identification and follow-up of HSE risk and the realisation of potential HSE improvements.
Result
One non-conformity was identified in connection with employee participation.
Two improvement points were also identified relating to arrangements for employee participation and risk management.
Statoil has been given a deadline of 1 September 2016 to report on how the non-conformity and improvement points will be dealt with.