The audit was carried out on 25 November 2015.

Background

The background to the audit included the submitted and processed plan for development and operation (PDO), our main priorities of management responsibilities and barriers, and performance of a series of FT projects within Statoil.

Objective

The objective of the audit was to follow up on experiences of the planning and execution of the Gullfaks Rimfaksdalen project with an emphasis on pipelines, subsea facilities, control cables and control systems, as well as to follow up Statoil's experiences of FT projects, and to ensure that the project is planned and executed in compliance with applicable regulations and recognised norms, and that regulatory requirements for health, safety and the environment are met.

Result

No non-conformities or improvement points were identified during the audit.