The objective of the audit was to monitor the fabrication of flexible risers, follow up the operator and supplier/subcontractor and verify that the project is being planned and executed in compliance with regulatory requirements.

Result

No non-conformities were identified.

Two improvement points were identified in connection with document management, and responsibility and authority.

Statoil has been given a deadline of 10 November 2015 to report on how the improvement points will be dealt with.

Non-conformity:

Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:

Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.