The audit was conducted on 15 October 2015.

Objective

The objective of the audit was to monitor how drilling and well planning in the Aasta Hansteen project is being carried out and what criteria Statoil are basing their choice of drilling and completion facilities for the development on.

Result

No non-conformities were identified during the audit.

Two improvement points were identified, relating to:

  • Verification of results from wellhead fatigue analyses
  • Project plan