Objective

The objective of the audit was to verify that OMV's anchoring analyses and verifications comply with the regulations.

Result

One non-conformity was identified in connection with analysis verification.

In addition, three improvement points were identified in connection with:

  • Calibration of model results
  • Description of meteorological and oceanographic conditions
  • The frequency response functions

OMV has been given a deadline of 10 July 2015 to report on how the non-conformity and improvement points will be dealt with.

Non-conformity:

Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:

Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.