Objective

The objective of the audit was to verify that Odfjell Drilling has good systems for the verification of structural and maritime systems, especially focused on inspection findings and ageing.

Result

No non-conformities were identified.

An improvement point was identified connected with the follow-up of subcontractors.

Odfjell Drilling has been given a deadline of 30 August 2015 to report on how the improvement point will be dealt with.

Non-conformity:

Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:

Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.