Objective

The objective of the audit was to acquire a status update for the project and to review the equipment that will be produced in Egersund. There was an additional objective of monitoring that the project has been planned and carried out in compliance with applicable regulations and recognised norms, and that requirements in the HSE regulations are provided for.

Result

No non-conformities or improvement points were identified.