The audit was conducted on 13 and 14 June 2023.

Objective

The objective of the audit was to verify that the project is being carried out in compliance with the HSE regulations, and that, through its project management, Vår Energi is ensuring that, in the project execution phase, they are reducing risk and preventing accidents during the start-up and operational phases.

Result

During the audit we identified one improvement concerning better planning.

What happens next?

We have asked Vår Energi for their assessment of the improvement point identified. The reply deadline is set at 1 September 2023.