The audit was conducted from 26 to 28 September 2022.

Objective

The audit was focused on ensuring that, when it is moved to the field for start-up, the facility is in a proper state of completion and that the project organisation has handed over the necessary documentation to the operational organisation.

Result

No non-conformities were identified.

One improvement point was identified in connection with a thickness deviation.

What happens next?

We have asked Equinor to provide us with its assessment of the improvement point observed. The reply deadline is set at 9 December 2022.