The audit was conducted from 19 to 23 October 2020.

Objective

The objective of the audit was to verify that there is a clear connection and consistency between management-defined plans and the actual condition of the facility. The audit monitored previous audits aimed at the company’s follow-up, corrosion under insulation and maintenance of jacket structures.

Result

In the audit, one non-conformity was identified relating to the control of failure mechanisms.

No improvement points were identified.

What happens next?

We have asked Equinor to report on how the non-conformity will be addressed. The reply deadline is set at 22 January 2021.