§ 86 Well control
In the event of a well control incident, it shall be possible to regain well control by intervening directly in or on the well or by drilling one (1) relief well. This applies to wells where planning of drilling activities has been decided on after 1 January 2016.
In special cases, drilling activities that require more than one (1) relief well to regain well control in the event of a well control incident, can be planned for. When planning such activities, the solutions for regaining well control shall be verified by a party of organisational independence, no later than three months before planned start-up.
Where capping can be a measure in a well control incident, the operator shall have access to capping equipment for subsea wells.
Plans that describe how to regain the well control, shall be prepared.